Data Center Buildout · Project Northfield · Phase 2 Live incident · GSU FAT fail · energization target Dec 27, '27
01Site & foundations
02Shell & MEP rough-in
03Equipment install
04Commissioning
05IST & energize
Jan '26 Jul '26 Jan '27 Jul '27 Dec '27
GSU FAT · FAILED GSU transformer failed FAT testing at OEM-A plant. Confirmed impact to Dec 27 energization target. Three options modeled — decision needed to hold target or move it.
Option A
Expedited rework at OEM-A + heavy-haul priority · hold Dec 27
+6 wks compressed install
Option B
Pull unit from OEM-B project coming online earlier · hold Dec 27
Donor project slips ~4 wks
Option C
Move energization to Feb 14, '28
49-day slip · tenant penalty